Rural Electrification & Network Renewal.
The Rural Electrification Scheme which was started over sixty four years ago has
been described as the greatest social revolution in Ireland since the Land
Reforms of the 1880's and 1890's which gave farmers the right to purchase their
land. A Rural Electrification Report, prepared by the Board at the request of
the Government was published by the Oireachtas in 1945 but implementation of the
scheme could not have commenced until 1946 because of war-time shortages
• Despite the supposed conservatism of farmers, Rural Ireland responded
enthusiastically to the opportunity offered for development.
• The advent of electric power utterly transformed rural life in all its aspects
- economic, social, and cultural.
• The ready availability of power made possible a rapid expansion in both
agricultural and industrial output in rural areas.
• It can probably be claimed, too, that without the benefit of a widespread
rural supply system, Ireland would have been unable to contemplate membership of
the European Economic Community.

The Rural Electrification Programme was planned on an area basis and for this
purpose the country was divided into 792 areas, priority being given to those
areas which yielded the highest revenue in relation to the capital cost of the
supply network. The Scheme quickly gathered momentum but there were fluctuations
in the pace at which it subsequently proceeded, due mainly to changes in
Government policy from time to time. In 1955, for example, subsidy was withdrawn
by the Government and not restored until 1958. In 1962 the Government decided to
accelerate the programme by increasing the subsidy from 50% to 75% for a period
of five years. In pursuance of this policy the Board undertook an intensive
campaign (including a re-canvass of unconnected houses) to bring supply to as
many houses as possible in the period. This scheme, known as Planned Post -
Development was so successful that by 1965, almost 300,000 rural houses (81% of
the total) were connected to the supply system at a total cost of £36 million.

The rapid economic developments of the 1960's had, however, created such a surge
in demand for new connections in rural areas that by 1970, it had become evident
the completion date for the Rural Scheme as a whole was a receding target. The
Board took the initiative in formulating new proposals aimed at completing the
Scheme by 1975. This third stage was completed in the late seventies bringing
expenditure on the Scheme to about £90 million by which time it was estimated
that about 98% of all homes in the country had supply.
In the earlier part of this decade the Irish economic performance was very
buoyant and the level of sustained growth achieved was unprecedented with the
result that the Irish economy was given the title the "Celtic Tiger". During the
last five to six years many of the electricity networks erected by ESB in the
days of Rural Electrification have been replaced and upgraded. ESB is continuing
to invest heavily to upgrade the existing network and is actively planing for
future requirements well into the next century. The "Network Renewal Project"
started in Yr 2004 and now is almost complete at a cost of €6 billion presented
many similar challenges to the development of the original Scheme but every
opportunity was taken to organise the work so as to minimise supply
interruptions for customers and disturbance to farm activities.
This level of investment was not only necessary but it will prove to be hugely
important to the economies and social life of midland counties and counties
located on the western seaboard. The capital investment programme was also
critical in ensuring that ESB can continue to deliver a first class service to
all its customers.
Brendan Delany ESB Archive & Heritage Manager